1A

August 24, 2026 – January 2027

Sewer Upgrades

Initial underground utility construction along the Broadway Avenue corridor.

1B

January 2027

Storm Drain Installation

Storm drainage infrastructure installation.

2A

February – July 2027

Site Improvements

Roadway and corridor construction continues.

2B

August – November 2027

Site Improvements

3

December 2027 – January 2028

Final Surface Improvements

Final roadway improvements, striping, and project completion.